Case Study: Malaysia LNG Plant achieves safe retractable flare maintenance with Conbit

A Conbit Case Study

Preview of the Malaysia LNG Plant Case Study

Malaysia LNG Plant completes flare maintenance in 45 days with Conbit

Malaysia LNG Plant faced a challenge with its retractable flare stack, where the flare tips and miter joints on the risers showed signs of buckling and required replacement. The company contracted Conbit's partner to perform this critical maintenance to ensure the facility's continued operation and safety.

Conbit provided a specialized crew that utilized the stack's own retractable derrick system to lower each riser section to the ground for maintenance. Working with local partners, the team safely executed the project over 45 consecutive days, replacing the components and reinstalling them without a significant decrease in flare capacity. The solution from Conbit was completed safely and on time.