A Conbit Case Study
The customer, Global Tech 1, an offshore wind farm developer, faced the challenge of installing and securing a new substation platform in the North Sea. They required the removal of all heavy lifting equipment and aids used to lower the platform's legs and secure it to the seafloor with suction anchors. Global Tech 1 GmbH, alongside Keppel Verolme, enlisted Conbit and its offshore lifting installation services due to the company's extensive experience in this complex field.
Conbit prepared extensive engineering plans and calculations, which were approved by the marine warranty surveyor DNV GL. The solution involved installing two custom-built lifting booms, each with a 12t capacity, to provide the necessary reach that the platform's crane lacked. This approach eliminated the need for costly hull reinforcements and crane upgrades. Conbit's solution successfully demobilized the equipment offshore, resulting in significant project efficiencies and cost savings for the client.