Case Study: GDF Suez E&P achieves cost-effective offshore crane replacement with Conbit

A Conbit Case Study

Preview of the GDF Suez E&P Case Study

GDF Suez E&P replaces 2 offshore cranes with Conbit

GDF Suez E&P Netherlands faced the challenge of removing two diesel-driven cranes from their L10-AP gas platform in the North Sea and replacing one of them with a new crane. The company contracted vendor Conbit to provide the best structural design and procedural solution for this offshore crane exchange.

Conbit's solution was to erect a temporary tower crane on a custom-designed base structure to decommission the old cranes and install the new one. This approach offered a significant cost advantage over using a more expensive crane vessel. The Conbit team also revised the crane boom rest and maintenance platform to accommodate the new crane's size and performed all necessary structural analyses.


View this case study…

Conbit

159 Case Studies