Case Study: Centrica Production Nederland BV achieves safe below-deck oil tank installation with Conbit

A Conbit Case Study

Preview of the Centrica Production Nederland BV Case Study

Centrica Production Nederland BV installs a diesel oil tank 133 km offshore with Conbit

The customer, Centrica Production Nederland BV, required the installation of a diesel oil storage tank on their Grove platform in the North Sea. The challenge involved performing this complex lift below the platform deck. Vendor Conbit was awarded a contract for transport and installation, leveraging their structural engineering and lifting expertise to provide a solution.

Conbit implemented an innovative lifting method using four synchronized hydraulic winches, a first-of-its-kind application for this configuration. The solution proved to be flexible and efficient, allowing the team to safely and rapidly lift the tank from a supply vessel and install it in its final location. This project successfully demonstrated Conbit's ability to perform below-deck lifting operations, providing platform operators with a safe and efficient alternative to using large crane vessels.


View this case study…