Aker BP, an independent oil and gas operator on the Norwegian continental shelf, needed a faster way to prepare for its weekly maintenance planning meeting. The offshore and onshore maintenance team spent up to 15 hours each week manually gathering data from multiple systems to create a spreadsheet showing the status of critical equipment. Cognite, using Cognite Data Fusion™, helped address this challenge.
Cognite implemented a critical equipment dashboard that combined contextualized data from four source systems and streamed it in real time to a Power BI dashboard. The solution gave Aker BP a color-coded overview of maintenance priorities and deeper access to work order details, reducing administrative effort and improving maintenance planning efficiency. The company saved up to 15 hours a week from automating data collection and gained a clearer, more effective view of critical equipment status.