NHS, one of the busiest healthcare providers in the UK, needed to cut energy costs and carbon emissions across a large, complex hospital estate while ensuring day-to-day clinical services were not disrupted. Centrica Business Solutions was appointed to deliver a commercial LED lighting upgrade, using smart LED lights, movement sensors, and remote-control technology.
Centrica Business Solutions implemented a £1 million phased replacement lighting programme, including bespoke solutions for more complex areas and careful project management to maintain service continuity. The first phase delivered £85,000 in annual energy savings, with the second phase forecast to add another £95,000, bringing total savings to £180,000 per year across 5,500 lights and a projected payback of under six years.