DPR Construction, a large general contractor, sought to streamline processes and reduce errors for its self-perform division on the major Palomar Medical Center West project. They needed an integrated solution to manage complex tasks like drywall installation for 20 miles of wall under a tight schedule. They turned to On Center Software and its solutions, including On-Screen Takeoff, Quick Bid, and Digital Production Control, to address these challenges.
By implementing On Center Software's automated takeoff, estimating, and labor-tracking solutions, DPR gained clear graphical reporting for client discussions and efficient project management by floor and area. This allowed for effective collaboration and adaptation as the project's critical path changed. Using On Center Software's tools, DPR successfully delivered the $600 million, 38-month Palomar Medical Center West project on time and within budget, managing a peak of 249 drywallers on-site.