Capstone Green Energy
110 Case Studies
A Capstone Green Energy Case Study
Citibank’s La Jolla, California office building needed a reliable way to provide electricity while also managing heating and cooling demands for the site. Capstone Green Energy supplied a microturbine-based solution that could support critical loads and help integrate onsite energy use more efficiently.
Capstone Green Energy’s system uses exhaust from a single microturbine to heat water for both space heating and cooling, feeding hot-water absorption chillers that deliver nearly 20 tons of air conditioning. The building also benefits from automatic dual-mode capability for blackout support, giving Citibank dependable power, heating, and cooling in one integrated solution.