Multiplex, the construction firm behind the One Leadenhall project in London, wanted a more efficient, data-driven way to manage a complex 33-floor build. Working with Buildots, they sought to move beyond subjective trade meetings, improve schedule and budget control, and get better visibility into subcontractor progress and design coordination.
Buildots implemented its AI-driven construction management platform to provide objective progress tracking, forecasting, and real-time site data. The solution helped Multiplex identify at-risk activities earlier, spot unfinished work before it spread to other floors, and tighten design coordination. As a result, Multiplex improved accountability, productivity, and proactive decision-making across the project.
Andrew Feighery