Intel turned to Buildots to help manage the enormous complexity of its fab construction program, which includes multiple semiconductor fabs spanning millions of square feet, thousands of workers, and more than 50,000 activities per project. Intel’s challenge was to keep projects on schedule, reduce costly rework, maintain accurate as-built models, and transfer best practices across a large, multi-site construction initiative.
Using Buildots’ AI-powered progress tracking platform, Intel gained automated delay forecasting, quality assurance, and benchmarking across projects. Buildots helped Intel detect issues early, resulting in an estimated 4.3% reduction in rework costs per fab, about 4 weeks of delays avoided per fab, and 1,176 model updates and changes per fab to keep construction models accurate and current.
Dan Doron
VP & GM of Foundry Construction Enterprise