EcoWorld London, part of EcoWorld International, used Buildots on the Aberfeldy Village development in London’s East India Docks area. The team needed better visibility and quality control to protect the critical “watertight” milestone, as a window subcontractor was falling behind and threatening delays across the project.
Buildots provided early warning alerts based on site data, helping EcoWorld identify the issue quickly and respond with a more structured process, increased labour, and a higher run rate. As a result, the watertight milestone was achieved ahead of schedule, with the subcontractor finishing 9 weeks early on a 65-week program.