JHL Constructors, a Centennial, Colorado–based builder, faced slow, manual closeouts—their punch lists lived in Excel and required duplicate data entry and constant coordination. Senior Project Manager James Torres introduced Bridgit Field to solve this gap, aiming to streamline punch walks, subcontractor coordination, and final project closeout.
By adopting Bridgit Field—an intuitive, customizable app used in the field and embraced even by subcontractors—JHL completed 2,000 closeout tasks on a 130,000 sq. ft. middle school in eight weeks (twice as fast as projected). The faster closeout cut superintendent labor costs significantly (about $54,400 saved on that project), freed Torres to manage other jobs, and prompted wider adoption across JHL’s project teams.
James Torres
Senior Project Manager