Choate Construction, an ENR Top Contractor founded in 1989, was building the $41M Rollins Campus Center when one of the worst winters in Southeast history cost the project 192 days of productivity and compressed a 21‑month schedule into 14 months. The team was hampered by truckloads of paper, manual workflows and initial resistance from superintendents to adopt new digital processes.
Choate’s VDC leaders standardized documentation with Bluebeam Revu, deploying iPads, field kiosks, hyperlinked PDFs, instant cloud updates and 3D PDFs while training superintendents on the spot. The changes saved over 45 days of field time, enabled on‑time delivery, set a company‑wide digital standard, and led to organization‑wide adoption of Revu, field monitors, and integrated training.