A BIM Track Case Study
SynthésArt, a company specializing in technical and architectural synthesis, faced significant coordination challenges on the vast new Jules Bordet Oncology Institute project. The complexity involved dozens of companies from a large joint venture, a very high density of building systems, and highly sensitive areas, all of which had to be coordinated under a tight deadline.
To solve this, they implemented BIM Track. The platform provided a centralized hub for clash resolution, allowing all partners to collaborate effectively regardless of their modeling software. As a result, nearly 90% of the 500 issues raised were resolved in under six months. BIM Track facilitated more productive coordination meetings and provided analytics that helped SynthésArt identify bottlenecks and hold partners accountable for their progress.