A BIM&CO Case Study
RTE (Réseau de Transport d’Électricité) faced the challenge of creating 3D models for its high-voltage substations and improving the reliability of its asset data through its ambitious JUMP project. To meet this challenge, the customer turned to BIM&CO and its Onfly solution.
BIM&CO implemented its Onfly platform, a centralized BIM library that streamlined the creation, validation, and reuse of objects. This solution provided RTE with a standardized process, resulting in over 100 substations being modeled and 2,500 objects created. BIM&CO's product helped cut production time in half, which sped up modeling and optimized costs.