Bentley
139 Case Studies
A Bentley Case Study
Mass Rapid Transit Corporation (MRT Corp) was delivering the 52.2 km, 35‑station KVMRT SSP metro line in Kuala Lumpur and faced massive coordination, data-management, and design‑clash challenges across 20+ disciplines. To reduce on‑site changes and boost productivity, MRT Corp mandated a BIM Level 2 workflow and selected Bentley’s OpenRail Connected Data Environment (including ProjectWise, AssetWise, ContextCapture, and MicroStation) to establish a single, controlled collaboration platform.
Bentley implemented a cloud‑hosted federated CDE that enabled 1,500+ users to collaborate on about 7,500 models and 280,000+ documents (2.3 TB), using reality modeling, federated visualization, and CMMS integration to validate designs and monitor construction. The Bentley solution significantly reduced design clashes and rework, increased productivity by 35%, supported 4D/5D planning and accurate quantity takeoffs, and improved asset handover and lifecycle management.
Poh Seng Tiok
Director, Planning and Design