Providence College faced a challenge with its central chiller plant nearing full capacity due to campus expansion. To avoid the multi-million dollar cost and major construction of installing a new chiller and replacing large chilled water lines, the college and its contractor, Arden Engineering, sought a solution to reduce chilled water demand. They turned to vendor Belimo and its Energy Valve product to address this issue.
Belimo implemented a solution by installing 22 of its cloud-connected Energy Valves across campus buildings. These valves optimized chilled water flow and maintained Delta T, which reduced overall demand. The results allowed the college to avoid purchasing a new chiller, saving an estimated $500,000 to $1,000,000, plus millions more in avoided construction costs. The project also increased system efficiency and provided valuable data for future improvements, supporting the college's sustainability goals.