C.R. Jackson, a Columbia, SC–based heavy civil contractor handling highway and road construction, paving, water/sewer and materials, had relied on HCSS Heavy Bid for estimating but struggled with the lack of integration with its accounting and scheduling tools. That disconnect slowed workflows and made bid preparation and schedule coordination more cumbersome.
The company switched to B2W Estimate (and later added B2W Track), which was up and running in just two days and integrates with major accounting and project-management packages including Maxwell StreetSmarts and Primavera Contractor. The unified system sped reporting between field and office, allowed drag-and-drop copying of estimate items with automatic cost updates, improved scheduling for complex A+B bids, and delivered measurable time savings and greater efficiency across estimating and field operations.
Kelly Coope
Division Project Manager