Husky Injection Molding Systems, a global manufacturer with offices and SharePoint farms worldwide, needed to consolidate and upgrade multiple legacy SharePoint environments (SPS/WSS 2001–2003 and MOSS 2007) to SharePoint 2010. The company required an expedited, granular migration that could reorganize thousands of team sites across disparate farms while minimizing disruption to day-to-day business.
Consulting partner imason used AvePoint’s DocAve Migrator to perform high-fidelity, scheduled migrations—moving ~800 GB and ~2,400 sites in under four months while consolidating about 350 site collections into 60. Large site collections were migrated outside business hours to limit impact; the result was a centralized SharePoint 2010 environment with improved performance and better-managed site architecture.
Mike Kozai
IT Manager, Husky Injection Molding Systems Ltd.