DT Midstream required substation design and engineering services for four new substations to support its natural gas pipeline operations across Louisiana. The challenge involved designing these critical power facilities, which included overhead lines up to 230 kV and transformer capacities up to 34 MVA, to ensure reliable power delivery to compressor and cryogenic plants. To meet this need, they engaged Audubon for its detailed engineering and design services.
Audubon provided a full-scope solution, delivering the engineering, design, automation, and equipment selection for all four substations. The project was completed on time and on budget, enabling DT Midstream's construction phase to begin on schedule. The successfully implemented substations and integrated power distribution centers ensured a reliable power supply for the customer's essential natural gas delivery infrastructure.