Case Study: Apache Corporation achieves 75,000 HP compression capacity with Audubon EPCM and commissioning

A Audubon Case Study

Preview of the Apache Corporation Case Study

Apache Corporation delivers 75,000 hp of compression with Audubon

Apache Corporation required the development of two new greenfield compressor stations in Toyah, Texas, to handle a significant flow rate of natural gas. To meet this challenge, they engaged vendor Audubon to provide comprehensive EPCM services for the project's execution.

Audubon delivered a full solution that included project management, detailed engineering, procurement support, and construction management. The resulting Cypress and Spruce compressor stations were successfully built, each featuring ten CAT 3612 engine-driven compressors for a total of 75,000 HP of compression, along with amine and dehydration units. Audubon also managed the project's start-up and commissioning, ensuring the new facilities were fully operational.


View this case study…

Audubon

76 Case Studies