The customer, a confidential energy infrastructure company, faced the challenge of building a new 2-Bcf/d LNG supply system under significant environmental and supply chain constraints. Poor soil conditions, coastal regulations, and a limited vendor network threatened the project. Audubon provided an integrated solution of engineering, procurement, and surveying services to develop this critical infrastructure.
Audubon delivered detailed engineering for a turbine-driven compression station and metering stations, along with full procurement and pipeline surveying. The solution resulted in the on-time delivery of the high-capacity LNG system, which was designed for environmental stability. Audubon's procurement team managed over $50 million in spending across 24 suppliers, and the project provided the customer with fully traceable and verifiable data for long-term asset management.