Applus+
42 Case Studies
A Applus+ Case Study
The Company, a major airport, faced the challenge of safely expanding its jet fuel storage and fuelling facilities to meet increasing aviation traffic demands. They commissioned vendor Applus+ Velosi to conduct a comprehensive Phase II Health, Safety and Environmental Impact Assessment (HSEIA) for the project's EPC phase.
Applus+ Velosi implemented a detailed HSEIA study, which included reviewing the Health, Safety and Environmental Management System, conducting an Occupational Health Risk Assessment, a Quantitative Risk Assessment, and updating the Emergency Response Plan. The study identified four major accident hazards and 30 medium and low risk hazards, providing appropriate recommendations for their management. Applus+ validated that ambient air quality standards were not exceeded and found noise levels to be well below allowable limits, ensuring the project's risks were reduced to acceptable and ALARP levels.
The Company