Morgan Sindall Infrastructure, working on the Northumberland Line rail project, faced significant challenges with its manual short-term planning process. The team relied on complex Excel spreadsheets that were prone to errors, difficult to maintain with multiple users, and lacked logical links between activities, leading to frustration and wasted time. To address this, they turned to the digital planning platform provided by Aphex.
By implementing Aphex, the team replaced their error-prone spreadsheets with an intuitive and interconnected platform. The solution provided a clear visual plan, simplified the four-week lookahead process, and enabled better forecasting. The results included a successful rollout with positive team adoption, a significant reduction in manual data entry, and the capture of more robust data. Aphex also provided an early warning system for delayed milestones through its Power BI integration, improving overall project reporting and performance.