Aphex
63 Case Studies
A Aphex Case Study
Mace was the general contractor managing the construction of a complex data centre for client Pure DC, a project that required intensive daily coordination between multiple contractors. The team faced significant challenges in managing overlapping work activities and avoiding site clashes using their previous spreadsheet-based system, leading them to seek a more robust solution. They implemented Aphex, a planning and coordination platform, to improve collaboration and visibility.
By using Aphex for daily action briefings and short-term lookahead planning, the Mace team gained a clear visual overview of all site activities. This allowed them to proactively identify and resolve clashes, manage exclusion zones for safety, and even handle temporary service requests efficiently. The implementation of Aphex resulted in transformational improvements in coordination, fewer on-site conflicts, and enhanced safety management, making daily meetings more effective and keeping the project progressing well.