The Independent Electricity System Operator (IESO) needed to improve grid resiliency, time-shift energy, and support increasing renewable integration while accessing ancillary services. Ameresco was engaged to deliver battery energy storage technology and services—including design-build, Energy as a Service, and operations and maintenance—to meet these challenges.
Ameresco designed, built, owns and operates two 2 MW, four-hour battery energy storage systems on the Newmarket–Tay distribution grid (4 MW total, 16 MWh) under a 10‑year Energy Storage Facility Agreement (infrastructure investment $14.6M CAD, agreement secured in 2015). Ameresco’s systems provide time-shifting of energy, ancillary services, and improved grid reliability and stability while enabling IESO market participation and delivering measurable capacity and operational benefits.