Case Study: Cannon Mountain achieves 30% energy reduction and $386K annual cost savings with Ameresco

A Ameresco Case Study

Preview of the Cannon Mountain Case Study

Cannon Mountain Reduces Energy Consumption by 30% After Efficiency Project

Cannon Mountain engaged Ameresco to address high energy use and aging infrastructure tied to its snowmaking and mountain operations. Under a state-funded energy performance contract, Ameresco delivered an energy efficiency initiative focused on reducing consumption, lowering costs, and meeting sustainability goals while keeping the project budget-neutral.

Ameresco installed energy efficiency and conservation measures—including replacement of 388 high‑energy snow guns, 1,200 feet of water/air lines, a new pump house, a main-trunk power line, new transformers, and upgraded lighting and weatherization—which resulted in a 30% reduction in energy consumption, expected annual savings of $386,000, and more than 2.3 million pounds of annual greenhouse gas reductions. The $5.1M project is on track to pay for itself within 16 years and also increased snowmaking capacity and power reliability at Cannon Mountain.


Open case study document...

Cannon Mountain

Jeffrey Rose

Department of Natural & Cultural Resources


Ameresco

139 Case Studies