The Oregon Department of Transportation partnered with Ameresco to upgrade its outdated street and tunnel lighting infrastructure. The challenge was to reduce long-term maintenance costs and lower carbon emissions across its network in the Portland Metro region.
Ameresco implemented an energy savings performance contract to replace over 8,000 high-pressure sodium lights with energy-efficient LED fixtures. The $18.6 million project, completed in December 2021, resulted in 50% energy savings per fixture and an estimated reduction of 3,500 metric tons of carbon emissions annually. The new LED lighting provided by Ameresco also features a much longer lifespan, significantly reducing future maintenance needs.