Bergstan in Botswana faced major civil engineering challenges from flat terrain, unpredictable existing services, and limited slope on infrastructure projects, all of which made careful design and level control essential. To manage these complex conditions, Bergstan used AllyCAD alongside Civil Designer for detailed planning in small sections, with close attention to levels and site constraints.
AllyCAD helped Bergstan handle the difficult topography and service clashes more effectively by supporting precise design work and iterative adjustments. The result was better management of sewer, road, and culvert layouts, fewer avoidable surprises on site, and improved handling of project risks and claims, which Bergstan estimated at 10–15% of project value due to unknown existing services.