Supercomputing Center needed mission-critical maintenance and operations support for its N+1 Tier 2 data centers, which were built to double HPC megawatts and required strict upkeep across complex electrical, cooling, backup power, and life-safety systems. To reduce downtime risk and control costs, the center sought a vendor that could meet demanding standards across multiple technical disciplines.
ABM Industries proposed a comprehensive, self-performed service plan for the facility, leveraging its experience with Tier 3 and Tier 4 data centers. ABM Industries handled mechanical maintenance, in-scope electrical system upgrades, daily operational rounds, vendor escorting, and ongoing maintenance of critical equipment, helping improve operations, reduce downtime, and generate cost savings while maintaining uptime protection and safety.
Supercomputing Center